Location
The power plant is located near the village Dolani, Stip, south from the city, on the left side of the Bregalnica river. The village is on 380m altitude.
Specifications
The installed capacity of the power plant is 1.490,580 kW. The average sunlight energy is 1530 KWh/m2. The land is 15 604 m2 big and 3.276 panels on 25 degrees angle (south side orientation) are placed on 7459,1 m2.
Natural environment influence
The energy generation from photovoltaic panels has positive influence on the environment and it is indirectly reducing the greenhouse gasses emission. This power plant is reducing emission of 13.705,00 kg CO2.